PropPin
Caution
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Mar 2027 per the RERA filing.

Promoter

Builder profile

Builder
ASHAPURA ESTATES

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700045776
Status
New
Stage
Certificate Signed
Possession
March 2027originally June 2026
Construction
56.6% complete
Units sold
135 of 222

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.