Lodha Crown Kolshet-Tower 1
MahaRERA P51700045858Clean record
32/1 PART,33/1 PART, Dhokali, 400607
Post your property hereOwn or renting out a unit in Lodha Crown Kolshet-Tower 1? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Dhokali come to you.
Sept 2026
Possession
81.8%
Built
1
Complaints
427
Units
Clean record
No delays, complaints or enforcement actions in the official disclosures we track.
Promoter
Builder profile
LODHA DEVELOPERS LIMITED
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Pradeep Kamble
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P51700045858
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2026originally March 2026
- Construction
- 81.8% complete
- Units sold
- 359 of 427
Similar projects in Dhokali
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Vakratunda Anantaraa Tower 1
DhokaliPoss. April 2032
Vakratunda Anantaraa Business Park
DhokaliPoss. October 2030
THE ICON PHASE 3
Dhokali84.6% builtPoss. December 20263 complaints
The Icon Phase 5
Dhokali83.4% builtPoss. December 2026
The Icon Phase 4
Dhokali75.2% builtPoss. December 20261 complaint
Y SQUARE
Dhokali50% builtPoss. April 20291 complaint
Lodha Crown Kolshet - Tower 2
Dhokali41.6% builtPoss. July 2027
Elanor - Tower 1
Dhokali11.8% builtPoss. December 2031
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.