High risk
  • Mortgaged to a lender (₹33 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹33 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Possession delayed ~3 yrs. Originally promised Jun 2026, now proposed Dec 2028 per the RERA filing.

Area guide

What it's like to buy in Kolset

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
RAUNAK AVENUE REALTY

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
10 FOLDS ARCHITECTS & CONSULTANTS

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700048307
Status
New
Stage
Certificate Signed
Possession
December 2028originally June 2026
Construction
33.5% complete
Units sold
8 of 72

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.