High risk
  • Possession delayed ~2 yrs. Originally promised Mar 2025, now proposed Mar 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
Kalyan–DombivliValue

Central-line volume market — affordable towers around busy junctions.

Growth drivers:
Metro 5, ring-road plans, the region's most accessible pricing.
Who buys here:
Budget-first buyers who commute the central line.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
PAWAN ENTERPRISES

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
CREDIBLE DESIGNS

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700048857
Status
New
Stage
Certificate Signed
Possession
March 2027originally March 2025
Construction
56.8% complete
Units sold
20 of 56

Similar projects in KALYAN

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.