PropPin
Caution
  • Possession date passed. The proposed possession date (Oct 2025) has passed with construction at 54.1%.

Promoter

Builder profile

Builder
BHOOMI HOMES

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700051538
Status
New
Stage
Certificate Signed
Possession
October 2025
Construction
54.1% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.