  • Promised amenities not started. Clubhouse is at 0% build with possession due May 2027 per the RERA filing.

Area guide

What it's like to buy in Kulgaon

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Ashish Waman Gole

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Hemant Vaidya

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700053040
Status
New
Stage
Certificate Signed
Possession
May 2027
Construction
50% complete
Units sold
12 of 78

Similar projects in Kulgaon

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.