Under construction

PATELS EIRENE

MahaRERA P51700054106High risk

by PRAMUKH DEVELOPERS

PLOT NO 277 CTS NO 4483 TO 4488 PLOT NO 280 CTS NO 4471 TO 4476, AMBERNATH EAST, 421501

Official record
Aug 2026
Possession
46.8%
Built
0
Complaints
60
Units
High risk
  • Behind schedule. Possession is due Aug 2026 but construction is only at 46.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2026 per the RERA filing.

Area guide

What it's like to buy in AMBERNATH EAST

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Ambernath / BadlapurValue

The value frontier beyond Kalyan β€” low-rise affordability, improving rail links.

Growth drivers:
Extended suburban rail, industrial-belt employment, lowest entry prices in MMR.
Who buys here:
First-home buyers stretching every rupee.

PropPin area guide β€” editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
PRAMUKH DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700054106
Status
New
Stage
Certificate Signed
Possession
August 2026
Construction
46.8% complete
Units sold
14 of 60

Similar projects in AMBERNATH EAST

Other MahaRERA-registered projects in the same locality β€” useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.