All RERA projects
🏗️
Under construction
PITAMBARE TOWER
MahaRERA P51700055596Caution
by ADITI BUILDERS AND DEVELOPERS
SURVEY NO 26/5, KHADAVALI, 421605
Post your property hereOwn or renting out a unit in PITAMBARE TOWER? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in KHADAVALI come to you.
Mar 2028
Possession
0%
Built
0
Complaints
29
Units
Caution
- Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Mar 2028 per the RERA filing.
Promoter
Builder profile
ADITI BUILDERS AND DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700055596
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2028originally December 2025
- Construction
- 0% complete
- Units sold
- 0 of 29
Similar projects in KHADAVALI
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
AARTI PARK
KHADAVALI18.2% builtPoss. December 2028
PRIYADARSHINI HEIGHTS
KHADAVALI9.1% builtPoss. October 2027
USHA JOSHI PARK PHASE III
KHADAVALI8.3% builtPoss. December 2028
ROYAL RESIDENCY
KHADAVALI6% builtPoss. January 2029
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.