Under construction
Belvedere I
MahaRERA P51700077599High risk
25/2A Part 25/2B Part, Hedutane, 421203
Post your property hereOwn or renting out a unit in Belvedere I? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Hedutane come to you.
Dec 2030
Possession
1.8%
Built
0
Complaints
95
Units
High risk
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- Possession delayed ~2 yrs. Originally promised Jul 2028, now proposed Dec 2030 per the RERA filing.
Area guide
What it's like to buy in Hedutane
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Lodha Developers Limited
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Pradeep Kamble
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P51700077599
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2030originally July 2028
- Construction
- 1.8% complete
- Units sold
- 0 of 95
Similar projects in Hedutane
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
BALAJI RESIDENCY COMPLEX
Hedutane90.6% builtPoss. December 2018
Fiora I
Hedutane17.3% builtPoss. February 2030
Belvedere-K
Hedutane11.4% builtPoss. September 2029
Belvedere J
Hedutane10.5% builtPoss. December 2029
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.