High risk
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~3 yrs. Originally promised Dec 2022, now proposed Jun 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 89.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.

Area guide

What it's like to buy in Kurla

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

MulundUpper-mid

Leafy eastern-suburb favourite with big redevelopment supply.

Growth drivers:
Eastern Express Highway, proposed Goregaon–Mulund link, mall belt.
Who buys here:
Eastern-suburb families upgrading within the area.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
JAI SUN MAVERICK REALTORS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800003963
Status
Ongoing
Stage
Certificate Signed
Possession
June 2026originally December 2022
Construction
89.9% complete
Units sold
14 of 63

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.