High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2020, now proposed Jun 2026 per the RERA filing.
  • 10 RERA complaints. 10 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 82.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.

Area guide

What it's like to buy in Borivali

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
M/S GAURI LAND DEVELOPERS LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
SAMEER KULKARNI

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51800004832
Status
Ongoing
Stage
Certificate Signed
Possession
June 2026originally December 2020
Construction
82.8% complete
Units sold
309 of 315

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.