High risk
  • Mortgaged to a lender (₹65 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹65 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Possession delayed ~6 yrs. Originally promised Dec 2021, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Area guide

What it's like to buy in Andheri

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Andheri WestUpper-mid

Entertainment-industry heartland — dense, lively, well connected.

Growth drivers:
Metro lines 1/2A, Lokhandwala–Versova redevelopment wave.
Who buys here:
Media professionals, first upgraders, rental investors.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Yura Business Park Private Limited

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Skyline Inframart Consultants LLP

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800005547
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally December 2021
Construction
54.5% complete
Units sold
54 of 59

Similar projects in Andheri

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.