MAHATMA JYOTIBA PHULE CHS LTD
by TRIDEVH CONSTRUCTION COMPANY
492-B, Kurla, 400081
- 5 appeals at MahaREAT. 5 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
- 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Area guide
What it's like to buy in Kurla
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Leafy eastern-suburb favourite with big redevelopment supply.
- Growth drivers:
- Eastern Express Highway, proposed Goregaon–Mulund link, mall belt.
- Who buys here:
- Eastern-suburb families upgrading within the area.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P51800006009
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2023
- Construction
- 64.2% complete
- Units sold
- 98 of 132
Similar projects in Kurla
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.