High risk
  • Possession delayed ~1 yr. Originally promised Apr 2021, now proposed Oct 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2022) has passed with construction at 43.8%.

Promoter

Builder profile

Builder
VaibhavLaxmi Builders and Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800006691
Status
Ongoing
Stage
Certificate Signed
Possession
October 2022originally April 2021
Construction
43.8% complete