High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2024, now proposed Dec 2027 per the RERA filing.

Area guide

What it's like to buy in Andheri

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
SANI MASCOT DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51800007030
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally December 2024
Construction
62.7% complete
Units sold
27 of 80

Similar projects in Andheri

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.