High risk
  • 4 appeals at MahaREAT. 4 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~7 yrs. Originally promised Dec 2020, now proposed Dec 2027 per the RERA filing.
  • High complaint rate. 5 complaints against only 6 sold units — a high rate for a project this size.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Kandivali / BorivaliMid-income

Self-sufficient Gujarati-dominated family belt beside the National Park.

Growth drivers:
Metro 2A/7, station upgrades, big-brand township launches.
Who buys here:
Families seeking space and community at sane prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Tuvin Consultancy LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
KEY ARCH

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800007223
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally December 2020
Construction
72.7% complete
Units sold
6 of 28

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.