PropPin
High risk
  • Possession delayed ~6 yrs. Originally promised Jun 2021, now proposed Dec 2026 per the RERA filing.
  • 9 RERA complaints. 9 complaint records are disclosed against this project on MahaRERA.

Promoter

Builder profile

Builder
DHRUVI PROPERTIES PVT LTD

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51800007232
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally June 2021
Construction
86.8% complete
Units sold
0 of 0

Similar projects in Andheri

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.