High risk
  • Mortgaged to a lender (₹205 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹205 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • 6 appeals at MahaREAT. 6 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~5 yrs. Originally promised Jun 2023, now proposed Dec 2027 per the RERA filing.
  • 57 RERA complaints. 57 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Promoter

Builder profile

Builder
RUPAREL SHREEJI CONSTRUCTION PVT LTD

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Rahul Kamathi

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800007630
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally June 2023
Construction
48.9% complete
Units sold
217 of 336

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.