Under construction
CALLISSA
MahaRERA P51800008237High risk
by RAMBHIA PROPERTIES PRIVATE LIMITED
1493 1494 1495 1501 1504 1505 1507 1508 1509A 1515, Borivali, 400095
Post your property hereOwn or renting out a unit in CALLISSA? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Borivali come to you.
Dec 2029
Possession
32.3%
Built
5
Complaints
101
Units
High risk
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- Possession delayed ~6 yrs. Originally promised Dec 2023, now proposed Dec 2029 per the RERA filing.
- High complaint rate. 5 complaints against only 20 sold units — a high rate for a project this size.
Promoter
Builder profile
RAMBHIA PROPERTIES PRIVATE LIMITED
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Architect
Design profile
SANDEEP PANDURANG VICHARE
Browse other projects associated with this architect to compare design and delivery patterns.
No other projects are linked to this architect yet.
Official RERA facts
- Registration
- P51800008237
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2029originally December 2023
- Construction
- 32.3% complete
- Units sold
- 20 of 101
Similar projects in Borivali
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Mehta Marquina 1978
BorivaliPoss. December 2030
JASWANTI SQUARE
BorivaliPoss. December 2028
NICCO SUNDERMILAN
BorivaliPoss. December 2029
AVYUKTA JAY ABHILASHA
BorivaliPoss. June 2029
VARDHAMAN
BorivaliPoss. December 2028
GOYAL MERIDIAN
BorivaliPoss. October 2029
MAULI PRIDE 1 BCDE
BorivaliPoss. December 2028
SHEETAL UPTOWN PHASE II
BorivaliPoss. December 20301 complaint
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.