Post your property hereOwn or renting out a unit in BIZ POINT? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Kurla come to you.
Dec 2027
Possession
90.2%
Built
1
Complaints
111
Units
High risk
- Possession delayed ~5 yrs. Originally promised Dec 2022, now proposed Dec 2027 per the RERA filing.
Ghatkopar / VikhroliUpper-mid
Metro-1 anchor with Godrej's Vikhroli land bank next door.
- Growth drivers:
- Metro 1 interchange, Eastern Express Highway, corporate campuses.
- Who buys here:
- Families wanting east-side connectivity to BKC/Fort.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
N N DATAR & ASSOCIATES
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Architect
Design profile
DEOLE BROS
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P51800009838
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2027originally December 2022
- Construction
- 90.2% complete
- Units sold
- 49 of 111
Similar projects in Kurla
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
VAIBHAV SEASONS
KurlaPoss. March 2030
Mahindra Rainforest Phase 2
KurlaPoss. December 2031
NARMADA PLAZA
KurlaPoss. December 2029
DAR US SALAM
KurlaPoss. June 20291 complaint
Agadh Sagar Co-Op Housing Society Ltd
KurlaPoss. December 2028
Prakkruti One
KurlaPoss. December 2029
CRESCENT WTC T2 PHASE II
KurlaPoss. August 2028
Ashford Regal - Phase IV- Wing C Project
KurlaPoss. June 2029
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.