LEVEL - The Residences
242Apt, 244, 246, 246/1-10,243, 265A, 248, 249 pt, Andheri, 400102
- Litigation pending (8). MahaRERA's litigation disclosure lists 8 pending cases against this project.
- Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
- 14 RERA complaints. 14 complaint records are disclosed against this project on MahaRERA.
Area guide
What it's like to buy in Andheri
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Entertainment-industry heartland — dense, lively, well connected.
- Growth drivers:
- Metro lines 1/2A, Lokhandwala–Versova redevelopment wave.
- Who buys here:
- Media professionals, first upgraders, rental investors.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51800011428
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2023
- Construction
- 99.5% complete
- Units sold
- 0 of 0
Similar projects in Andheri
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.