All RERA projects
🏗️
Under construction
Godrej RKS
MahaRERA P51800023915High risk
by Godrej Projects Development Limited
Comprised within CTS no 673, 673/1 to 673/20, 783 part, Chembur, 400071
Post your property hereOwn or renting out a unit in Godrej RKS? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Chembur come to you.
Dec 2024
Possession
78.4%
Built
8
Complaints
149
Units
High risk
- 8 RERA complaints. 8 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 78.4%.
Kurla / ChemburMid-income
Central crossroads reborn via freeway and Metro links.
- Growth drivers:
- Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
- Who buys here:
- BKC-bound professionals and long-time Chembur families.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
Godrej Projects Development Limited
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800023915
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2024
- Construction
- 78.4% complete
- Units sold
- 132 of 149
Similar projects in Chembur
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Prime Vista
ChemburPoss. June 2031
DELKEIN EDGE
ChemburPoss. February 2028
SUNRISE HEIGHTS
ChemburPoss. December 2028
STARVIEW
ChemburPoss. December 2030
Yash Residency
ChemburPoss. January 2030
Swastik Bliss
ChemburPoss. December 2029
Apoorva Rise
Chembur97.7% builtPoss. December 2024
Udyam
Chembur90.9% builtPoss. March 20231 complaint