Under construction
URBAN WAVES
MahaRERA P51800026269High risk
B-906 B/1 PT, B-1152 PT, Andheri, 400050
Post your property hereOwn or renting out a unit in URBAN WAVES? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Andheri come to you.
Jul 2027
Possession
47%
Built
1
Complaints
34
Units
High risk
- Possession delayed ~2 yrs. Originally promised Jun 2025, now proposed Jul 2027 per the RERA filing.
- Behind schedule. Possession is due Jul 2027 but construction is only at 47%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2027 per the RERA filing.
Area guide
What it's like to buy in Andheri
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
HAREKRUSHNA DEVELOPERS LLP
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800026269
- Status
- New
- Stage
- Certificate Signed
- Possession
- July 2027originally June 2025
- Construction
- 47% complete
- Units sold
- 20 of 34
Similar projects in Andheri
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
LUMINAARA
AndheriPoss. December 2029
153 EAST
AndheriPoss. December 2028
Kripa Aqua
AndheriPoss. December 2028
SAI SIDDHI RESIDENCY
AndheriPoss. May 2029
Shree Sadhana Co-Operative Housing Society Limited
AndheriPoss. December 2029
Sayba Noor
AndheriPoss. June 2029
Skyline Serenity
AndheriPoss. December 2030
Morya Galani Homes
AndheriPoss. January 2032
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.