  • Possession delayed ~2 yrs. Originally promised Jun 2024, now proposed Jun 2026 per the RERA filing.
  • 8 RERA complaints. 8 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 67.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.

Area guide

What it's like to buy in Kurla

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Kurla / ChemburMid-income

Central crossroads reborn via freeway and Metro links.

Growth drivers:
Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
Who buys here:
BKC-bound professionals and long-time Chembur families.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Shree Siddhivinayak Classic Construction Private Limited

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800026450
Status
New
Stage
Certificate Signed
Possession
June 2026originally June 2024
Construction
67.7% complete
Units sold
66 of 155

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.