High risk
  • 3 appeals at MahaREAT. 3 complaints against this project have been escalated to the appellate tribunal (MahaREAT) β€” a stronger signal than the complaint being merely filed.
  • Possession delayed ~3 yrs. Originally promised Jun 2024, now proposed Jun 2027 per the RERA filing.
  • 11 RERA complaints. 11 complaint records are disclosed against this project on MahaRERA.
  • Behind schedule. Possession is due Jun 2027 but construction is only at 27.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Area guide

What it's like to buy in Chembur

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Kurla / ChemburMid-income

Central crossroads reborn via freeway and Metro links.

Growth drivers:
Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
Who buys here:
BKC-bound professionals and long-time Chembur families.

PropPin area guide β€” editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
PRIYA CONSTRUCTIONS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800026869
Status
New
Stage
Certificate Signed
Possession
June 2027originally June 2024
Construction
27.3% complete
Units sold
96 of 196

Similar projects in Chembur

Other MahaRERA-registered projects in the same locality β€” useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.