PropPin
High risk
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 40.9%.

Promoter

Builder profile

Builder
Lotus Enterprises

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800027068
Status
New
Stage
Certificate Signed
Possession
June 2022
Construction
40.9% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.