SHREE LAXMI VANDAN
160A AND 160B, KANDIVALI WEST, 400067
- Possession delayed ~2 yrs. Originally promised Jun 2023, now proposed Jun 2025 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 90.9%.
Area guide
What it's like to buy in KANDIVALI WEST
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Retail-and-BPO hub with dense mid-income housing on both sides.
- Growth drivers:
- Mindspace offices, Link Road retail, Metro 2A.
- Who buys here:
- Mid-income families, first-time buyers.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800027654
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2025originally June 2023
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in KANDIVALI WEST
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.