High risk
  • Possession delayed ~3 yrs. Originally promised Mar 2023, now proposed Jun 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 64.7%.

Area guide

What it's like to buy in Borivali

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
KRISHNAN AND KAMAL ASSOCIATES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
MITIE Designers and planners pvt

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800031850
Status
New
Stage
Certificate Signed
Possession
June 2026originally March 2023
Construction
64.7% complete
Units sold
26 of 135

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.