High risk
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 40%.
  • Promised amenities not started. Gymnasium, Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2023 per the RERA filing.

Area guide

What it's like to buy in KANDIVALI WEST, MUMBAI

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Kandivali / BorivaliMid-income

Self-sufficient Gujarati-dominated family belt beside the National Park.

Growth drivers:
Metro 2A/7, station upgrades, big-brand township launches.
Who buys here:
Families seeking space and community at sane prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
WESTIN SANKALP DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800031940
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
40% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.