High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2024, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Promoter

Builder profile

Builder
ANGEL CONSTRUCTION COMPANY

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
VASTU KHUBI

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51800032085
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2024
Construction
63.7% complete
Units sold
99 of 168

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.