All RERA projects
🏗️
Under construction
MONARCH WEST VIEW
MahaRERA P51800046029High risk
71B, SANTACRUZ WEST, 400054
Post your property hereOwn or renting out a unit in MONARCH WEST VIEW? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in SANTACRUZ WEST come to you.
Apr 2025
Possession
90.9%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Apr 2025) has passed with construction at 90.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2025 per the RERA filing.
Promoter
Builder profile
MONARCH CONSTRUCTION
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800046029
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2025
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in SANTACRUZ WEST
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
SMRUTI BY RANGOLI DEVELOPERS
SANTACRUZ WESTPoss. January 2029
CYRILYN
SANTACRUZ WESTPoss. December 2026
TRITON
SANTACRUZ WEST90.5% builtPoss. July 2025
SEASONS TRIMURTI
SANTACRUZ WEST73.2% builtPoss. December 2025
VARDHMAN CASTLE PHASE I
SANTACRUZ WEST0.2% builtPoss. December 2023
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.