PropPin
High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2027 per the RERA filing.

Area guide

What it's like to buy in Kurla

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
K V DEVCON LIMITED LIABILITY PARTNERSHIP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
VINOD GAIKWAD

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800047715
Status
New
Stage
Certificate Signed
Possession
December 2027
Construction
17.8% complete
Units sold
2 of 38

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.