High risk
  • Possession delayed ~2 yrs. Originally promised May 2025, now proposed May 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due May 2027 per the RERA filing.

Area guide

What it's like to buy in Kurla

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
M/S SANA ENTERPRISES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Supreme Project Management Consultant & Associates

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51800047918
Status
New
Stage
Certificate Signed
Possession
May 2027originally May 2025
Construction
75.5% complete
Units sold
5 of 31

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.