Under construction
VIKAS 11
MahaRERA P51800048458High risk
551/17, Kurla, 400080
Post your property hereOwn or renting out a unit in VIKAS 11? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Kurla come to you.
Jun 2027
Possession
46.1%
Built
0
Complaints
0
Units
High risk
- Behind schedule. Possession is due Jun 2027 but construction is only at 46.1%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.
Area guide
What it's like to buy in Kurla
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
VIKAS LIFESPACE LLP
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Shraddha Joshi
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P51800048458
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2027
- Construction
- 46.1% complete
- Units sold
- 0 of 0
Similar projects in Kurla
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Skyline
KurlaPoss. December 2029
Ekvira and Saishakti
KurlaPoss. December 2029
Tilak Safalya
KurlaPoss. December 2028
Horizon Antara
KurlaPoss. June 2028
La Italia
KurlaPoss. June 2028
AKASSH AMAZONIA TOWER 1
KurlaPoss. June 2030
EASTERN BAY
KurlaPoss. October 2029
Sayba Swarna
KurlaPoss. December 2027
Data sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.