High risk
  • Possession delayed ~1 yr. Originally promised Sept 2025, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 40.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Kandivali / BorivaliMid-income

Self-sufficient Gujarati-dominated family belt beside the National Park.

Growth drivers:
Metro 2A/7, station upgrades, big-brand township launches.
Who buys here:
Families seeking space and community at sane prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
LIVING HABITATS PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
PARIN SHAH

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800051382
Status
New
Stage
Certificate Signed
Possession
December 2026originally September 2025
Construction
40.1% complete
Units sold
22 of 60

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.