PropPin
Caution
  • Behind schedule. Possession is due Nov 2026 but construction is only at 45.5%.

Promoter

Builder profile

Builder
EMPIRE REALTY

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
CHIRAG RAYANI

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800054561
Status
New
Stage
Certificate Signed
Possession
November 2026
Construction
45.5% complete
Units sold
7 of 43

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.