PropPin
🏗️
Under construction

Ruparel Pristine

MahaRERA P51800055522High risk

by Ruparel Pristine

Plot no 36 Survey no 236 CTS no 194/A/1, Kurla, 400077

Official record
Dec 2026
Possession
48.3%
Built
0
Complaints
72
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 48.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Area guide

What it's like to buy in Kurla

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Ruparel Pristine

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51800055522
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
48.3% complete
Units sold
39 of 72

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.