PropPin
High risk
  • Behind schedule. Possession is due Feb 2027 but construction is only at 49.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Feb 2027 per the RERA filing.

Promoter

Builder profile

Builder
FLUSHEL PREMISES CO OP SOCIETY LTD

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51800056239
Status
New
Stage
Certificate Signed
Possession
February 2027
Construction
49.5% complete
Units sold
0 of 0

Similar projects in Andheri

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.