PropPin
Caution
  • Behind schedule. Possession is due Dec 2026 but construction is only at 18.2%.

Area guide

What it's like to buy in Kurla

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

PowaiPremium

Lakeside planned township with an IT/startup ecosystem.

Growth drivers:
Hiranandani stock, IIT-B halo, LBS/JVLR connectivity.
Who buys here:
Tech professionals and startup founders.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
MASS EMINENCE

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
VIEW DIMENSIONS PROPRIETOR ZEESHAN ANSARI

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51800076726
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
18.2% complete
Units sold
0 of 0

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.