PropPin
High risk
  • 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.
  • Behind schedule. Possession is due Aug 2026 but construction is only at 40.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2026 per the RERA filing.

Area guide

What it's like to buy in Borivali

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Dahisar / Mira RoadValue

The city's northern value frontier, densifying fast.

Growth drivers:
Metro 9 extension, spillover from Borivali pricing.
Who buys here:
First-time buyers stretching for a 1–2 BHK.

PropPin area guide β€” editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
RAJ CAPITAL

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
CHIRAG S RAYANI S RAYANI

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51800079347
Status
New
Stage
Certificate Signed
Possession
August 2026
Construction
40.5% complete
Units sold
0 of 0

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality β€” useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.