High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Possession delayed ~1 yr. Originally promised Oct 2025, now proposed Nov 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2026 per the RERA filing.

Area guide

What it's like to buy in Near Crawford Market

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Beauty Lifestyles and Homes Pvt. Ltd.

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51900002372
Status
Ongoing
Stage
Certificate Signed
Possession
November 2026originally October 2025
Construction
97.5% complete
Units sold
55 of 56

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.