High risk
  • Possession delayed ~7 yrs. Originally promised Dec 2019, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 42.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Dahisar / Mira RoadValue

The city's northern value frontier, densifying fast.

Growth drivers:
Metro 9 extension, spillover from Borivali pricing.
Who buys here:
First-time buyers stretching for a 1–2 BHK.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
PRATHAM DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Chirag S Rayani

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51900002771
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2019
Construction
42.7% complete
Units sold
0 of 11

Similar projects in Mumbai City

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.