PropPin
High risk
  • Litigation pending (4). MahaRERA's litigation disclosure lists 4 pending cases against this project.
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~6 yrs. Originally promised Dec 2019, now proposed Jun 2026 per the RERA filing.
  • 8 RERA complaints. 8 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 83.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.

Promoter

Builder profile

Builder
Ruparel Estates India Pvt Ltd

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Mr Rahul Kamathi Kamathi

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51900005988
Status
Ongoing
Stage
Certificate Signed
Possession
June 2026originally December 2019
Construction
83.6% complete
Units sold
30 of 98

Similar projects in Mumbai City

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.