High risk
  • 6 appeals at MahaREAT. 6 complaints against this project have been escalated to the appellate tribunal (MahaREAT) β€” a stronger signal than the complaint being merely filed.
  • Possession delayed ~3 yrs. Originally promised Jun 2023, now proposed Jul 2026 per the RERA filing.
  • 11 RERA complaints. 11 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Jul 2026) has passed with construction at 64.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2026 per the RERA filing.

Area guide

What it's like to buy in Mumbai City

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

PowaiPremium

Lakeside planned township with an IT/startup ecosystem.

Growth drivers:
Hiranandani stock, IIT-B halo, LBS/JVLR connectivity.
Who buys here:
Tech professionals and startup founders.

PropPin area guide β€” editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
DILIP ESTATE & TOWN PLANNERS PVT LTD

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
HAFEEZ CONTRACTOR

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51900006119
Status
Ongoing
Stage
Certificate Signed
Possession
July 2026originally June 2023
Construction
64.9% complete
Units sold
28 of 42

Similar projects in Mumbai City

Other MahaRERA-registered projects in the same locality β€” useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.