High risk
  • Possession delayed ~6 yrs. Originally promised Oct 2020, now proposed Mar 2027 per the RERA filing.
  • High complaint rate. 4 complaints against only 13 sold units β€” a high rate for a project this size.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Area guide

What it's like to buy in Mumbai City

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Kurla / ChemburMid-income

Central crossroads reborn via freeway and Metro links.

Growth drivers:
Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
Who buys here:
BKC-bound professionals and long-time Chembur families.

PropPin area guide β€” editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
PRABHAV ARISHA

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51900007376
Status
New
Stage
Certificate Signed
Possession
March 2027originally October 2020
Construction
77.3% complete
Units sold
13 of 23

Similar projects in Mumbai City

Other MahaRERA-registered projects in the same locality β€” useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.