High risk
  • Litigation pending (3). MahaRERA's litigation disclosure lists 3 pending cases against this project.
  • 6 appeals at MahaREAT. 6 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Jun 2027 per the RERA filing.
  • 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.
Girgaon / Grant RoadPremium

Heritage chawl-and-wadi belt in cluster redevelopment mode.

Growth drivers:
Cluster redevelopment policy, Metro 3, Coastal Road.
Who buys here:
South-Bombay natives staying local in new towers.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
HILTON INFRASTRUCTURE

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
SHAIKH & ASSOCIATES

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51900009939
Status
Ongoing
Stage
Certificate Signed
Possession
June 2027originally December 2022
Construction
97.5% complete
Units sold
124 of 220

Similar projects in Mumbai City

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.