Siddha Sky Phase 3

MahaRERA P51900021044High risk

by M/s. Sejal Shakti Realtors LLP

6 pt,16 pt to 21 pt of salt pan division and 12pt of sion division, Mumbai City, 400037

Official record
Dec 2026
Possession
45%
Built
4
Complaints
357
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 45%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.

Area guide

What it's like to buy in Mumbai City

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
M/s. Sejal Shakti Realtors LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51900021044
Status
New
Stage
Certificate Signed
Possession
December 2026originally May 2026
Construction
45% complete
Units sold
277 of 357

Similar projects in Mumbai City

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.