High risk
  • Mortgaged to a lender (₹25 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹25 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 99.5%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Jun 2026 per the RERA filing.

Area guide

What it's like to buy in Ward GNorth

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
AYG HOMES CONSTRUCTIONS PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Madhur Yogesh Gupta

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51900031858
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
99.5% complete
Units sold
11 of 36

Similar projects in Ward GNorth

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.