MahaRERA P51900049038High risk

by Baysquare Constructions

C.S.No.585/6 and 585A/6 Sion Division, Plot No.285 and 285A, Mumbai City, 400022

Official record
Dec 2026
Possession
53.4%
Built
0
Complaints
36
Units
High risk
  • Possession delayed ~1 yr. Originally promised Nov 2025, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.

Area guide

What it's like to buy in Mumbai City

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Sion / MatungaUpper-mid

Old central Bombay — colleges, gardens and society redevelopment.

Growth drivers:
Central location, rail junctions, redevelopment of 60s societies.
Who buys here:
Central-line families and South Indian community roots.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Baysquare Constructions

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Ar Amod Mandlik

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51900049038
Status
New
Stage
Certificate Signed
Possession
December 2026originally November 2025
Construction
53.4% complete
Units sold
1 of 36

Similar projects in Mumbai City

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.