YASH HEIGHTS
MahaRERA P52000007304High risk
PLOT NO 9 SEC 9 ULWE TAL PANVEL DIST RAIGAD, Navi Mumbai, 400706
Post your property hereOwn or renting out a unit in YASH HEIGHTS? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Navi Mumbai come to you.
Jun 2019
Possession
73.2%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Jun 2019) has passed with construction at 73.2%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2019 per the RERA filing.
Navi Mumbai (Vashi–Nerul)Mid-income
Planned-city order — wide roads, node markets, established social infra.
- Growth drivers:
- Atal Setu (MTHL), metro lines, the upcoming Navi Mumbai airport.
- Who buys here:
- Professionals wanting planned-city living with airport-corridor upside.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
Yash Developers
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52000007304
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2019
- Construction
- 73.2% complete
- Units sold
- 0 of 0
Similar projects in Navi Mumbai
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Shreepati Gurukrupa
Navi MumbaiPoss. June 2029
79 LAKEVIEW
Navi MumbaiPoss. July 2029
Jai Mata Di
Navi MumbaiPoss. November 2026
GeeCee Aspira 206
Navi Mumbai100% builtPoss. August 2023
SEA REGENCY
Navi Mumbai98.2% builtPoss. December 20223 complaints
ARIHANT ANSHULA
Navi Mumbai85.5% builtPoss. December 20191 complaint
BALAJI VISTA
Navi Mumbai84.1% builtPoss. May 2027
J. K. Paradise
Navi Mumbai58.3% builtPoss. December 2026
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.